Flagstaff Meadows Unit 3
Project
Flagstaff Meadows Unit 3
Owner
Capstone Homes
EMC Role
Prime Contractor
Engineer
Shephard Wesnitzer, Inc.
Project Overview
Eagle Mountain was contracted to complete the Flagstaff Meadows Phase 1 subdivision. This project was started roughly 10 years prior and abandoned so there was a small portion of infrastructure the EMC repaired, tested and commissioned as well as the remaining section of the subdivision. Through winter conditions and hard rock EMC was able to deliver this project to the owner on time so the housing crews could get started in spring. This project consisted of:
- 19,110 CY of cut to fill earthwork
- 3,680 LF of new sewer line
- 3,800 LF of new waterline
- 154 New services
- 10,362 LF of Curb & Gutter
- 17,961 SY of asphalt
- 41,272 SF of new sidewalk